The project was approved by the municipal council in 2003. In addition to that an official decree was published by the Lebanese government in the same year. Unfortunately, all roads were published under one decree. The condition now is very complicated. Many meetings were conducted to minimize the negative impact of the implementation of the decree. Unfortunately we could not succeed to find a solution.
Based on the above information, the Municipal Council decided to split the implementation of the decree into several parts. We hopes to cooperate in a productive and open way with the concerned habitants for the benefit and the future of Kafaraka
International Labour Organization agreed to finance the construction of the three roads. The project is expected to be implemented in August 2019.
The project was accomplished in December 2020. Around 2 km of new roads was constructed.